A government client has a statutory payment clock. A private client does not get that clock just because a prompt payment act exists in the same state. On 13 November 2026 I could verify the federal rule, Wisconsin state agencies, Texas governmental entities, New York state agencies, and the Illinois compiled paragraph that still says 60 days. If your client is a company, stop here and use the contract.
The private-client math is a different page. Can I charge interest on a late invoice is the contract question. The late fee calculator by state is the rate when a private invoice is silent. UK and EU commercial invoices are a third statute. Do not mix the three in one demand letter.
I would not put "prompt payment act" in a reminder to a private client, even a client that feels as slow as a bureau. The phrase makes a true private debt look like you cited the wrong law, and the client who has a lawyer will notice.
A Wisconsin agency invoice, with the arithmetic
The Department of Administration says interest is 12 percent, compounded monthly. Section 16.528 says the interest runs from the 31st day and is compounded monthly. Here is one month and two months on a $6,000 invoice, using that 12 percent figure and a monthly compound, which is 1 percent of the balance each month.
- One month: 1 percent of $6,000 is $60. Interest is $60.
- Two months: the second month is 1 percent of $6,060, which is $60.60. Interest for two months is $60 plus $60.60, which is $120.60.
- The department also says not to add your own late fee on top. If you do, they send the invoice back, and the clock starts over on the corrected bill.
That $60 is not a number you type onto an invoice to a Madison design studio. It is the interest a Wisconsin state agency adds when it misses its own clock.
The clocks I could verify
Checked 13 November 2026. Private clients are not in this table.
United States
- Statute: 31 USC 3902 and 3903, the Prompt Payment Act.
- If the contract sets a due date, that date is the required payment date. If it does not, the required payment date is 30 days after a proper invoice is received, with exceptions in the section for meat, perishable agricultural commodities, dairy, and construction. Section 3903(a).
- An invoice that is not proper has to be returned not later than 7 days after receipt, with the reasons. Days past that 7-day return come off the agency's time to pay. Section 3903(a)(7).
- Interest runs from the day after the required payment date until the day of payment, at the Treasury rate published in the Federal Register for 41 USC 7109. An interest penalty of $1 or more is paid without a request. Section 3902.
- An unpaid interest penalty that sits for 30 days is added to the principal, and the penalty then accrues on that added amount. Section 3902(e). Lack of funds is not an excuse. Section 3902(d).
- Construction: an approved progress payment that remains unpaid for more than 14 days after the designated office receives the request can draw interest, unless the solicitation specified a longer inspection period. Retained amounts, if the contract sets no release date, are tied to the 30th day after final acceptance. Section 3903(a)(6).
Wisconsin state agencies
- Statute: Wis. Stat. section 16.528. The Department of Administration's prompt payment page restates the clock for suppliers.
- For orders or contracts entered on and after the first day of the third 12-month period beginning after 1 February 1987, payment is timely if it is mailed, delivered, or transferred within 30 days after receipt of a properly completed invoice or receipt and acceptance of the property or service, whichever is later. Section 16.528(2)(b)3. That is the clock for a current contract. Older contracts in the same subsection had 45 days.
- Interest runs from the 31st day, at the rate in section 71.82(1)(a), compounded monthly. The Department of Administration states that rate as 12 percent, compounded monthly.
- A principal contractor on an agency order has to pay a subcontractor for satisfactory work no later than 7 days after the contractor receives the agency's payment. Section 16.528(2m).
- The department's page says a supplier may not add a late fee, a penalty, or any other extra fee to a state invoice. The wrong fee gets the invoice returned.
Texas governmental entities
- Statute: Texas Government Code section 2251.021, on the Texas statutes site.
- For a contract executed on or after 1 September 1987, a payment is overdue on the 31st day after the later of three dates: the entity receives the goods, the service is completed, or the entity receives the invoice.
- A political subdivision whose governing body meets only once a month or less frequently is overdue on the 46th day, for a contract executed on or after 1 September 1993.
- A state agency payment for certain legal services under section 402.0212 is overdue on the 46th day after the agency receives the invoice.
- I am not printing this year's interest percent. The rate is in section 2251.025, and I did not open that section on this check.
New York state agencies
- Statute: State Finance Law section 179-f, Article 11-A, on the Senate's compiled laws page.
- The required payment date is 30 calendar days, excluding legal holidays, after receipt of an invoice for the amount due, except for the cases the section lists. A small business's required payment date is 15 calendar days, excluding legal holidays, if it submits the invoice electronically in line with the state's accounting system and identifies that it is seeking expedited payment as a small business.
- Final payments on highway construction contracts are 75 calendar days, excluding legal holidays, unless another exception applies.
- Interest is not paid if the amount computed under section 179-g is less than $10. I did not open section 179-g, so I am not printing the current overpayment rate.
- An audit hold, an inspection period, a missing appropriation, a federal review, or goods and services that were not delivered as the contract requires can extend the date by the time it takes to clear that condition. The section says the agency still has to make reasonable efforts to act quickly.
Illinois
- Statute: State Prompt Payment Act, 30 ILCS 540/3-2, compiled text on the General Assembly site.
- Paragraph (1), for a bill that is not a Public Aid Code Article V bill and not the case in paragraph (1.05), says the bill must be paid or the payment issued within 60 days of receipt of a proper bill or invoice. After that, an interest penalty of 1.0 percent of any amount approved and unpaid is added for each month, or fraction of a month, until final payment.
- I am not describing paragraph (1.05). It is an exception inside the same section, and I did not restate it. Do not collapse Illinois to one number.
- The same page says an individual interest payment of $5 or less is not paid, with a stated exception, and that interest penalties of $50 or more are paid automatically when the section requires them and the contract did not set different late-payment terms in writing.
How to count a federal invoice
An agency receives a proper invoice on 1 March, and the contract does not set a pay date. Section 3903 makes the required payment date 30 days after receipt. Thirty days after 1 March is 31 March. Interest, if the agency is late, starts on 1 April, the day after the required payment date, under section 3902(b). I am not multiplying that by a percent, because the Treasury rate for that period is a Federal Register figure I am not inventing.
If the invoice was missing the order number, the agency's job is to send it back within 7 days and say why. Your job is to send a proper invoice, not to start the interest argument on a bill they were allowed to reject.
States left out
California's Government Code prompt payment sections, Florida's local government act, and most other states are not in the table. I did not open those texts on 13 November 2026. A national chart that fills them from a trade-association PDF is how a wrong day count gets onto a demand. Open the statute for the agency that actually owes you, or leave the citation off the letter.
If the client is private, the next document is the contract and a normal reminder. Use the payment reminder generator for that email. Use the demand letter generator when you are ready to name the amount and the date. Name a prompt payment section only when the client is the government that section names.
Keep reading
- A private client's late fee is a contract question, not a prompt payment act.
- UK and EU statutory interest is a different statute, for commercial invoices in those places.
- How to write a late fee into the next private agreement.