You have to record a mechanics lien on the state's own calendar, and that calendar is not 90 days from the end of the project in every state. California, Texas, and Florida are the three I opened on 13 November 2026. Florida is 90 days from your own last day of work. Texas is the 15th day of a later month. California, for someone who is not the direct contractor, is the earlier of 90 days after completion or 30 days after a recorded notice of completion. Miss the one that applies to you and the lien is gone.
This page is for trades. It is not a late-fee worksheet. The money on a draw is the contractor late fee calculator. The bill itself is the contractor invoice generator. The years you have to sue on a contract, where those were verified, are the statute of limitations by state. A lien deadline is shorter than those years, and it runs while you are still hoping the check will arrive.
I would not diary "90 days from completion" on a Texas commercial job. The statute gives you the 15th of the fourth month after the month the work ended, and a 90-day habit will either rush you or, worse, convince you that you still have time on the 16th.
Three calendars for a job that ended in March
Use 1 March as the last relevant day, and do not reuse the date across states. These are recording deadlines from the sections, not the earlier notices and not the lawsuit that has to follow the recording.
Florida. You last furnished labor or materials on 1 March. Section 713.08(5) says the claim of lien may be recorded during the work or after it, but not later than 90 days after your final furnishing. Ninety days after 1 March is 30 May. March has 31 days, so 30 days lands on 31 March, 60 days lands on 30 April, and 90 days lands on 30 May. If someone else is still on the site in June, your 90 days did not move with them.
Texas, original contractor, not a residential project. The work was completed in March. Section 53.052(a) says not later than the 15th day of the fourth month after that month. April is the first month, May the second, June the third, July the fourth. The date is 15 July. The same contractor on a residential project uses the third month, which is 15 June. A claimant who is not the original contractor, on a non-residential job, files by the 15th day of the fourth month after the later of the month they last provided labor or materials or the month specially fabricated materials should have been delivered.
California, not the direct contractor. You have stopped work. Completion of the work of improvement is 1 March, and the owner records a notice of completion on 10 March. Section 8414 says you must record before the earlier of 90 days after completion or 30 days after that recorded notice. Ninety days after 1 March is 30 May. Thirty days after 10 March is 9 April. The statute says you record before the earlier of those times, so the line in this example is before 9 April, not a plan to record on 9 April. If the owner never records the notice, the 90-day branch is the one you have, and you still cannot record until you have ceased to provide work.
The statutes
Checked 13 November 2026. Read the row for your role. The other role is a different deadline.
California
- Statute: Civil Code section 8414, on the legislature's site. It applies to a claimant other than a direct contractor.
- You may not enforce the lien unless you record the claim after you cease to provide work, and before the earlier of 90 days after completion of the work of improvement or 30 days after the owner records a notice of completion or cessation.
- I did not open the direct contractor's section on this check. Do not borrow 8414 for the prime.
- The section's history note says it was added by Stats. 2010, chapter 697, operative 1 July 2012. I am not describing preliminary notice or the deadline to file suit after you record.
Texas
- Statute: Property Code section 53.052, on the Texas Constitution and Statutes site.
- Original contractor, not residential: the 15th day of the fourth month after the month the work was completed, terminated, or abandoned.
- Original contractor, residential: the 15th day of the third month after that month.
- Other claimants, not residential: the 15th day of the fourth month after the later of the month they last provided labor or materials, or the month specially fabricated materials would normally have been delivered.
- Other claimants, residential: the 15th day of the third month after that later month.
- Retainage, for a claimant other than the original contractor: the 15th day of the third month after the month the original contract was completed, terminated, or abandoned. Subsection (d).
- File the affidavit in the county where the improvements are located. A clerk's indexing mistake does not invalidate a filed affidavit. Subsection (e).
Florida
- Statute: section 713.08, 2025 Florida Statutes, on the Senate's site.
- The claim of lien may be recorded during the work or afterward, but not later than 90 days after the final furnishing of the labor, services, or materials by the lienor. Subsection (5).
- If the original contract is terminated under section 713.07(4), a claim for a lien that attached before termination may not be recorded after 90 days following the termination or 90 days after the lienor's final furnishing, whichever is first.
- The claim is recorded in the clerk's office. If the property is in two or more counties, record in each.
- Serve the claim on the owner. Failure to serve it in the manner of section 713.18, before recording or within 15 days after recording, makes the claim voidable to the extent the delay prejudiced someone entitled to rely on the service. That service rule is not the 90-day recording rule. Both can matter.
- The claim has to be signed and sworn. Subsection (2). I am not describing the notice to owner, which is a separate section.
What to do with the date
Write the last day you were on the job in the file the day you leave, not the day you get angry. Florida and the Texas subcontractor rule both care about your last furnishing. A diary that says "project ends in June" is the wrong anchor if you finished in March.
Then open the statute for the state where the property sits, for your role, before you tell a client you still have a lien. This page is three states. A job in another state is not covered by a feeling that 90 days is standard. Send the invoice from the contractor invoice generator while the date is still comfortable, and keep the pay application that shows the last day on site.
Keep reading
- A late fee is the invoice. A lien is the property. They are not substitutes.
- Collections is another path, and it is not a lien.
- The years you have to sue on a contract are a different clock from the days you have to record a lien.